nfosigw 11
 

2016

Construction of the unit for recovery of electrolytic waste in BOLESŁAW RECYCLING Sp. z o.o.

The project was implemented in 2016 according to agreement No : 1/2016/Wn-06/OZ-UI/U from 23.06.2016 with subsequent amendments.

Total cost of the project is 4 075 790,00 PLN.

Financial subsidy from NFOŚiGW in the amount of 1 000 000,00 PLN as a cancellation of a part of the loan granted on the basis of the loan agreement  No: 426/2004/Wn-6/OZ-UI/P from 13.10.2004  with subsequent amendments.

2011 - 2012

Extension of the waelz kilns installation in BOLESŁAW RECYCLING Sp. z o. o.

Financially supported by the National Environmental Protection and Water Management Found

Project was implemented in 2011-2012

Total cost of the project is: 61.620.526,78 PLN Financial support in a form of a loan from NFOŚiGW in the amount of: 28.081.650,00 PLN according to the agreement No. BR/DE/U29/11